Amazon has registered plans with Texas regulators for a 1.2 million-square-foot building at its planned robotics manufacturing plant in Southeast Austin, with construction of the first phase scheduled to begin Nov. 16 and finish by July 13, 2027.
The filing, registered Monday, Oct. 19, with the Texas Department of Licensing and Regulation, lists the project as “Project Toaster – Core and Shell” at 475 Patton Ave. in Travis County. The owner is Amazon.com Services LLC, and the design firm is WSP USA. The filing estimates the cost of the work at $100 million and describes it as new construction: civil site development plus the core and shell of a single building for an advanced manufacturing facility, divided into four areas for offices, the factory, casting and a utility plant.
The $100 million figure covers only this core-and-shell phase registered with the state, not the whole project. Amazon described the overall development as “multi-billion-dollar” when it announced the plant in August.
The jobs were announced in August
The filing does not change the jobs picture. On Aug. 19, Amazon said the facility would create “300 – 500 high-paying jobs in manufacturing and engineering” and would produce robotics systems that “work alongside Amazon’s employees to handle repetitive tasks and heavy lifting.” Those positions are projections, not current openings, and Amazon has not published a hiring timeline.
In July, Austin Assistant City Manager Eric Johnson told a City Council work session that the facility would add hundreds of jobs averaging $75,000 to $150,000 in pay and could open by late 2027, Community Impact reported. Amazon did not confirm a development schedule when it announced the project, the outlet said.
Amazon already employs about 17,000 people in Austin and 86,000 across Texas, according to the company.
Part of the Dog's Head redevelopment
The plant is the first major tenant identified for Dog’s Head, a redevelopment of nearly 2,650 acres near Austin-Bergstrom International Airport, much of it a former sand-and-gravel mining site, led by Endeavor Real Estate Group, the Austin American-Statesman reported. Community Impact reported that the robotics project covers roughly 300 acres and was first reviewed under the placeholder name “Project Toaster.”
Austin Mayor Kirk Watson said in August that “Amazon asked for no economic incentives, no public money.” Separately, the City Council approved a tax increment reinvestment zone and a preliminary financing plan for Dog’s Head in July. That plan uses part of the new tax revenue generated in the district to reimburse Endeavor for roads, utilities and other infrastructure. Travis County has been asked to join the financing district, but its votes on the matter have stalled, according to the Statesman.
In September, the Save Our Springs Alliance, People Organized in Defense of Earth and Her Resources and several residents sued the city, the mayor and the City Council, arguing that the reinvestment zone is “an unconstitutional gift of public funds,” the Statesman reported. The suit seeks to block the broader financing plan, not the Amazon project specifically, and no ruling has been reported.
Training and research ties
Amazon’s August announcement pointed to Austin’s engineering talent and university partnerships as reasons for the location. The company said its Amazon Science Hub with the University of Texas, focused on machine learning and robotics research, has been active since 2023, and that 14,500 of its Texas employees have taken part in its Career Choice education program through 35 colleges and universities, including Austin Community College. Those programs predate the factory and are not tied to its hiring.
For job seekers, the near-term work is construction. The state filing covers building the shell through mid-2027, and the manufacturing and engineering roles Amazon has projected would follow only once the plant is built and equipped.
Sources
- Texas Department of Licensing and Regulation, TABS project registration TABS2027003891, “Project Toaster – Core and Shell,” registered October 19, 2026. https://www.tdlr.texas.gov/TABS/Search/Print/TABS2027003891
- Austin American-Statesman via Yahoo News, “Amazon trucks forward with Dog’s Head robotics factory despite development lawsuit,” October 20, 2026. https://www.yahoo.com/news/us/articles/amazon-trucks-forward-dogs-head-192018734.html
- Amazon, announcement of new manufacturing facility in Austin, Texas, August 19, 2026. https://press.aboutamazon.com/2026/8/amazon-announces-new-manufacturing-facility-in-austin-texas
- Community Impact, “Amazon picks East Austin for multi-billion dollar robotics facility,” August 19, 2026. https://communityimpact.com/east-austin/development/amazon-picks-east-austin-for-multi-billion-dollar-robotics-facility/
- Community Impact, “Austin leaders ready for Dog’s Head financing vote; Amazon robotics facility revealed as anchor project,” July 21, 2026. https://communityimpact.com/east-austin/government/austin-leaders-ready-for-dogs-head-financing-vote-amazon-robotics-facility-revealed-as-anchor-project/
Featured photo: An Amazon drive unit robot on display at Amazon's BRS2 fulfilment centre in Swindon, England, March 26, 2025. Representative image of Amazon warehouse robotics; not the planned Austin factory or its products. Photo: Auledas, via Wikimedia Commons (CC BY 4.0). Cropped from the original.